Clubhouse build history

Thursday, 6 November 2008

Building to start next week

Now that the site has been cleared and the ground made ready, the main contractors will start work on the building on November 10th - how exciting! There is a build time of 20-weeks giving a completion date of March 20th (although this could be sooner) - just in time for the start of the new paddling season.

The build project will include, boat storage space, changing rooms and toilets, and a meeting room. Outside includes the secure compound, landscaping, a landing stage parallel to the shore and a slipway.

Working parties have been set up to report back to the main TWA committee - if you feel you have any expertise, skills or can contribute in some way, please get in touch with Ruth. The groups are: racking & storage space; facilities & meeting room; and grants & fundraising.

We are still fundraising and finding grants for a floating pontoon, boat racking and interior fittings for the meeting room and 'kitchen' area.

Ruth